Both cranes at 80 Clarkson have now come down and limestone façade installation is close to complete, moving the project into fit-out ahead of completion this year.
The two towers, which stand at 490 and 420 feet, were financed with a $985 million construction loan from Cale Street Partners and Farallon Capital Management, the largest residential construction loan issued in New York City since the pandemic.
The Team Behind the Build
| Developers | Zeckendorf Development, Atlas Capital Group and The Baupost Group |
| Design Architect | COOKFOX Architects |
| Architect of Record | SLCE Architects |
| General Contractor | Suffolk Construction |
What It Means for Hiring
As 80 Clarkson draws to a close, it is easy to forget the people behind the build. The numerous individuals who have spent months and years of their lives developing, designing, managing, and building our skylines often find themselves wondering what's next.
If this is you, feel free to get in touch.
Sources
- Commercial Observer: Manhattan Residential Towers Project Nabs $985M Loan
- Field Condition: 80 Clarkson construction update, January 2026
More From Market Watch

Market Insight: New York vs Miami Office Demand
Manhattan office leasing is at its strongest since 2000 and conversions are set to more than double, while Miami has too little office space for demand. Fit-out, conversion and high-rise delivery draw on the same pool of project leaders.

Behind the Build: JPMorganChase Global HQ, 270 Park Avenue
JRM Construction Management delivered the interior build-out of 28 floors, more than 1.3 million square feet, inside JPMorgan Chase's 1,388-foot tower at 270 Park Avenue.

Behind the Build: Bonhams U.S. HQ, Steinway Hall
Bonhams' new 42,000-square-foot U.S. flagship spans four floors of Steinway Hall on West 57th Street and is about 30% larger than its former Madison Avenue home.